Verwaltungsgericht Entscheid VB.2018.00609 vom 29.08.2019 (ZH)
Date:29.08.2019
Force of law:Dieser Entscheid ist rechtskräftig.
Summary:On January 23, 2018, A AG received the building permit for an extension of a building in Uerikon. C AG, on the other hand, filed a complaint, which was approved on August 15, 2018. The A AG then filed an appeal and demanded the cancellation of the appeal decision and the confirmation of the building permit. The Administrative court decided that the planned increase is admissible and dismissed the appeal of C AG. The costs of the procedure amount to Fr. 4'650.-, which the C AG must bear. The judge is male, the losing party is C AG, a company.
Rule of Law:-
BGE reference::131 III 345; 139 III 404;
Comment:
-

Please note that there is no claim to topicality/accuracy/format and/or completeness and that therefore any guarantee is excluded. Original decisions may be ordered or made on the basis of the competent court.

Click here to return to the page search engine.